Progress Update 1

March 2025: With the move now in motion to our new TechPoint Group location, we’ll be providing regular progress updates to keep you informed. Here’s what’s been accomplished so far and information on what’s coming next.

Having joined the TechPoint Group in April 2024, our search for the ideal facility began in June 2024, with a focus on finding a site that meets our high standards for innovation, sustainability, and operational efficiency.

Milestone
Date
Status
Site Selection Begins
June 2024
Completed
Lease Signed & Planning Permission Submitted
Feb 2025
Completed
Building Development Work Begins
Apr – May 2025
In Progress
Facility Fit-Out & Equipment Installation
Jun – Aug 2025
Upcoming
Go-Live & Operational Transition
Sep 2025
Upcoming

Milestone 1

February 2025: Lease signed and planning permission submitted.

After extensive evaluation of over 70 properties, a new-build facility in Basingstoke, Hampshire has been chosen.

Gtec New Facility 1
Gtec New Facility 2

This selection was based upon a strict criteria to ensure that the new building meets TechPoint Group’s business requirements and very high standards.

Gemini New Facilty Building 1-min
Gemini New Facilty Building 2-min
Gemini New Facilty Building 3-min

Milestone 2

January-March 2025: Design creation, final signoff and Planning Approvals.

Our new TechPoint Group facility was previously unoccupied and has in excess of 60,000 sq ft.of space. This will enable us to have all departments in one building across 3 floors and offers flexible space to allow for future growth with excellent local authority support. The new building design has been completed and approved.

MileStone2-min

The new building will not only increase efficiency but also allow us to take on more complex projects including those with enhanced compliance requirements for sensitive and high-precision projects such as those in Aerospace and Defence. It will also enable us to continue to invest in new technologies allowing us to deliver the highest quality solutions to all of our customers.

The shop floor will be fully ESD-compliant with enhanced lighting, climate control, and an optimised layout to support productivity and quality control.

The facility is also sustainable as standard offering a number of  key benefits.

Building fabric designed and constructed to very high standards of insulation and air tightness

Roof-mounted solar photovoltaic (PV) system

Harvesting and cleaning rainwater to use in our WCs rather than drawing from the mains

Water saving taps and WCs saving gallons of water a year

Leak-detection system designed to accurately identify potential water leaks

EV charging points for colleague and customer use

Providing us with the ability to accurately monitor and measure energy consumption across the site

Key Customer Benefits

The move marks a major milestone in our TechPoint Group journey, and we will be sharing regular updates on our progress in the coming months. Stay tuned for more insights as we prepare for our scheduled full go-live in September 2025!

What is happening next month?